 The national energyBureau about print and distribute"Photovoltaic (pv)Interim measures for power generation operation regulation "notice
Each resident agencies, the provinces (autonomous regions and municipalities directly under the central government) national development and reform commission (energy bureau), the xinjiang production and construction corps of the national development and reform commission, the relevant power enterprise:   
  To promote the pv industryHealthy development, strengthenPhotovoltaic power generationGrid operation regulation, we compiled the "interim measures for photovoltaic power generation operation regulation" and have been, director of the office meeting examined and approved, printed and distributed to you now, please comply with them.
The national energy administration
On November 26, 2013
The first chapter the general
  Article 1 with aTo strengthen supervision, ensure the photovoltaic power generation systemsEffective operation, optimize the energy supply way, promote energy conservation and emissions reduction, according to the renewable energy law of the People's Republic of China, the electricity regulatory ordinance and other laws and regulations and the relevant provisions of the state, these measures are formulated.
  Article 2:This method is suitable for the gridPhotovoltaic power stationThe project anddistributedPhotovoltaic power generation project.
  Article 3 thePower administrative department under the state council and its dispatched institutions in accordance with the method of photovoltaic power generation project of interconnection, operation, trading and information disclosure regulation.No unit or individual is found violation of these measures and the relevant provisions of the state,Can complain to the power administrative department under the state council and its dispatched institutions and report, the state council department in charge of energy and its dispatched institutions shall be dealt with according to law.
  Article 4.Photovoltaic power generation project operation main body and power grid enterprises shall abide by the electric power business license system, photovoltaic power generation related business in accordance with law, and accept the supervision power administrative department under the state council and its dispatched institutions.
The second chapter content
  Article 5.Power administrative department under the state council and its dispatched institutions of photovoltaic power generation project operation main body and the grid electricity licensing system of the enterpriseBesides, regulation.In addition to the implementation of the electric power business license by the regulation the exemption of photovoltaic power generation project, the other main grid photovoltaic power generation project operation should apply for electric power business licenses.Licensed operators shall keep the license conditions, the licensing items or registered items change, shall go through the procedures of alteration according to regulations.
  Article 6.Power administrative department under the state council and its dispatched institutions shall, in accordance with the relevant regulations of photovoltaic power quality regulation.Photovoltaic power generation and network power quality should be consistent with national standards, to ensure the reliable operation of power grid.
  Article 7.Power administrative department under the state council and its dispatched institutions to form a complete set of photovoltaic power grid construction regulation.Access to the public grid photovoltaic power generation project, access to the system engineering and access caused part of the public network reconstruction is power grid enterprise investment construction.Access to the user side of photovoltaic power generation project, access systems engineering construction by project operation principal investment, access to cause the public power grid renovation part by power grid enterprises invest in the construction.
  Article 8. Power administrative department under the state council and its dispatched institutions of grid-connected photovoltaic (pv) service regulation.Power grid enterprises shall, according to the principle of active service, concise and efficient, set up and improve the photovoltaic power station project after web service process, and provides the online transaction process, the relevant policy explanation, grid work progress inquiry and cooperate with parallel debugging and acceptance, etc.
Power grid enterprises shall provide convenience for distributed photovoltaic access conditions, the grid application acceptance, access system scheme designing, contract and agreement signed acceptance, interconnection and parallel debugging service in the whole process, according to the principle of "foreign", simplify the procedure.Power grid enterprises for distributed photovoltaic power generation project system reserve capacity fee and related services.
  Article 9.Power administrative department under the state council and its dispatched institutions to link time limit of grid-connected photovoltaic (pv) regulation.Grid photovoltaic power station project time limit in accordance with the relevant provisions of the national energy administration.
Distributed photovoltaic power projects, power grid enterprises from the date of receipt of the application for interconnection, the project owners shall be 25 working days to provide access to system solutions;Since the project owners to confirm access system scheme within five working days, provide access to network opinion letter, accordingly to carry out the project project owner for the record and engineering design and other follow-up work;Since grid acceptance and parallel debugging the acceptance of the completed within 10 working days pass electric energy metering device installation services, and with the project owner shall, in accordance with the requirements 杭弁 electricity contracts and interconnection agreement;Since the mark for the electric energy metering device interconnection within 10 working days after the installation is complete organization acceptance and parallel debugging, to provide project owners acceptance, after debugging through directly into parallel operation, acceptance criteria according to the relevant regulations of the state.If acceptance is unqualified, power grid enterprises should propose solutions to the project owners.
  Article 10.Power administrative department under the state council and its dispatched institutions of photovoltaic power generation project 杭弁 electricity contract and interconnection agreement has been signed, execution and registration regulation.
Power grid enterprise should with photovoltaic power station project operating subject 杭弁 electricity contracts and grid scheduling agreement, signed contracts and agreements shall be in conformity with the relevant provisions of the state, and in the contract and agreement signed within 10 working days the local agency energy department under the state council for the record.Photovoltaic power station 杭弁 electrical contract and grid scheduling agreement template, will power administrative department under the state council jointly with the administrative department for industry and commerce shall be formulated separately.
Power grid enterprise shall comply with the relevant provisions in a timely manner with distributed photovoltaic power generation project operation main body interconnection agreement and contract 杭弁 electricity.
  Article 11.Power administrative department under the state council and its dispatched institutions of power dispatching mechanism priority scheduling of photovoltaic power regulation.Electric power dispatching institution shall, in accordance with relevant state regulations on renewable energy generation to get to the Internet, power generation scheduling plan and organize their implementation.Electric power dispatching institution in addition to the force majeure or endanger the case of grid security and stability, shall not be restricted photovoltaic output.
Endanger grid security and stability "as mentioned in the present measures, shall be formulated by the state council and its dispatched institutions recognized by the competent department of energy.
Photovoltaic power generation project operation main body should abide by the relevant provisions of the power grid operation management, obey traffic command and dispatch command execution.
  Article 12.Power administrative department under the state council and its dispatched institutions for grid enterprises acquire the situation of the photovoltaic power regulation.
Power grid enterprise shall buy all the grid electricity within range of photovoltaic power generation project access.Due to force majeure or endanger grid security and stability, not a full acquisition, power grid enterprises shall timely will not full access to the Internet time, cause the information such as notify photovoltaic power generation project operation main body, and the energy of the state council department in charge of local agency for the record.
  Article 13. Power administrative department under the state council and its dispatched institutions of grid-connected photovoltaic (pv) operation maintenance regulation.
Grid photovoltaic power station project operation main body responsible for photovoltaic power station within the site collection of electrical circuits and booster, operation, maintenance and management of grid enterprises are responsible for photovoltaic power plant auxiliary power sent out engineering and public power grid operation, maintenance and management.Power grid enterprise schedule grid equipment maintenance should not affect send power grid photovoltaic power station, and three months in advance written notice to grid photovoltaic power station project operation.
Distributed photovoltaic projects can be under the guidance of power grid enterprises operating subject, responsible for photovoltaic power generation equipment operation, maintenance and project management.
  Article 14.Power administrative department under the state council and its dispatched institutions shall, in accordance with the relevant regulations of photovoltaic power and Internet regulation power measurement situation.
Photovoltaic power station project online electricity metering point Settings in the boundary of property right in principle, the measurement on the power project.Power grid enterprises are responsible for regular testing table, device configuration and testing shall meet about electricity metering technology and industry standards and regulations of the state.
Power grid enterprises for distributed photovoltaic power generation projects should be installed two sets of metering device, to full capacity, power metering, respectively.
  Article 15. Power administrative department under the state council and its dispatched institutions of photovoltaic electricity settlement regulation.
Photovoltaic power generation project electricity settlement in accordance with the relevant provisions.With natural human operating subject, power grid enterprises should try to simplify procedures, provide convenient settlement services.
  Article 16.Power administrative department under the state council and its dispatched institutions of photovoltaic power generation subsidies implementation regulation.
Power grid enterprises shall be in accordance with the subsidy standards approved by the state, timely, full specified amount pay subsidies.
The third chapter regulation
  Article 17. The local agency energy department under the state council and provincial energy departments should strengthen the regulation of photovoltaic power generation project management and information sharing, to formorganicCollaboration, is responsible for the work mechanism of the division of labor.
  Article 18.Power grid enterprise should to the region of the dispatched institutions shall submit quarterly energy department under the state council the following information:
  1Grid access for the photovoltaic power generation project, including access, access capacity, voltage level grid access time, etc.
  2Grid trading. Photovoltaic power generation projects, including the capacity, since the power consumption, electricity on the Internet, online shopping power and so on.
  3Photovoltaic power station project encountered in the process of parallel operation of important issues.
Grid photovoltaic power station operation main body should be monitored according to the industry quality supervision and regulation, information report will be run on a regular basis, and the occurrence of accidents and important issues in a timely manner to the province (city) of the local agency report energy department under the state council。
Power administrative department under the state council to perform regulatory responsibilities and its dispatched institutions according to the needs of photovoltaic power generation operations may be required subject and power grid enterprises shall submit other documents and data related to regulation.
  Article 19. Power administrative department under the state council and its dispatched institutions conduct site inspection can take the following measures:
  1. Check into the grid photovoltaic power plant and power grid enterprises;
  2Photovoltaic power generation project. Ask and dispatching agency staff, requiring them to explain the relevant inspection matters;
  3Looking up and duplicating and documents and materials relating to the inspection items, may be transferred, hidden or break down the documents and data shall be sealed;
  4For inspection, found in violation of the law shall have the right to corrected on the spot or require corrections within a time limit.
  Article 20.Photovoltaic power generation project operation main body and the grid enterprise grid can not reach an agreement, affect the normal power trading, the state council department in charge of energy and its dispatched institutions shall coordinate;After coordination is still fail to reach an agreement, the departments of energy and its dispatched institutions shall, in accordance with the relevant provisions of the state council shall be ruled.
Power grid company and photovoltaic power generation project operation main body for the contract dispute, can apply for mediation to power administrative department under the state council and its dispatched institutions.
  Article 21.Energy of the state council and its dispatched institutions to the public by the competent department of the national photovoltaic operating situation, the electric power enterprises to the relevant state regulations on renewable energy policy, implementation, etc.
  Article 22. Power grid company and photovoltaic power generation project operation subject in violation of the provisions of these measures, the state council department in charge of energy and its dispatched institutions can be in accordance with the law of the People's Republic of China renewable energy law and the electricity regulatory ordinance shall be investigated for their responsibilities.
Power grid enterprises fail to complete the acquisition of renewable energy power, thereby causing loss to the photovoltaic power generation project operation main body economy, shall, in accordance with the law of the People's Republic of China renewable energy law rules shall bear the liability for compensation.
The fourth chapter bylaws
  Article 23.National energy administration shall be responsible for the interpretation of these procedures, the resident agencies according to local actual situation to formulate regulatory rules.
Article 24. The measures from the date of release, is valid for 3 years.